Hi Paul - Can you set-up approvals (or milestone) in task template? It seems like you cannot. When you add the template to the project, you'd then have to manually change the subtask to Approval or Milestone. Is that right? Thanks!
Hide Replies 3
Avatar
Administrator
paulminors
You sure can. In the template editor, click on the task and you can change the task type at the top.Uploaded Image
Hide Replies 2
Avatar Placeholder
amymendez
Perfect, thank you! As a follow-up. I do not have Approval as an option. Is that a Business feature? We are on the Premium account.
Hide Replies 1
Avatar
Administrator
paulminors
Yes, Approval is a Business feature.